‘Holly’ and ‘Ivy’ speed up Whiteball Tunnel repairs

A THREE-WEEK closure of the West of England main line between Taunton and Exeter saw essential repairs made to two Victorian tunnels on the route. 

Whiteball Tunnel, between Taunton and Tiverton Parkway, was closed from February 18 until March 8 while Network Rail relined its walls with concrete to prevent loose masonry and bricks falling onto trains. 

The work was carried out with the assistance of two remotely controlled robots, nicknamed ‘Holly’ and ‘Ivy’, which sprayed 830 cubic metres of concrete onto the 170-year-old tunnel walls in just 21 days – a much faster rate than traditional techniques. 

Whiteball Tunnel, on the Taunton to Exeter route, during a three-week closure to reline the 170-year-old brickwork with sprayed concrete. NETWORK RAIL

During the closure, drainage improvements were also made to reduce the chance of flooding. 

At the same time, GWR train services were also reduced between Exeter and Plymouth as NR undertook track repairs in one of the twin bores of Marley Tunnel, near Totnes, in Devon. 

Trains continued to run, but capacity was reduced as only one track was available on this section.

Read more News and Features in the April 2019 issue of The RM –on sale now!

Enjoy more of The Railway Magazine reading every month. Click here to subscribe.

Comments

comments

source= https://www.railwaymagazine.co.uk/9609/holly-and-ivy-speed-up-whiteball-tunnel-repairs/

Bir Cevap Yazın

Bu site istenmeyenleri azaltmak için Akismet kullanır. Yorum verilerinizin nasıl işlendiğini öğrenin.

Top