Alstom Completes Interlocking System in Turkey Yurtdışı Haberleri by railsistem - Şubat 22, 20210 Alstom has completed and put into service its interlocking system on 328km of the Eskisehir-Kutahya-Balikesir mainline for its client, Turkish State Railway Administration (TCDD). The project was delivered in eight sections. Alstom completed and commissioned the interlocking system for the first five sections – covering more than 182km and encompassing the telecommunications and traffic control centre – on 5 December 2020. It then completed and commissioned the remaining three sections, measuring 146km on 5 February 2021. source= https://railway-news.com/alstom-completes-interlocking-system-in-turkey/ Paylaşmak Güzeldir... Facebook üzerinde paylaş (Yeni pencerede açılır) Facebook X'te paylaş (Yeni pencerede açılır) X LinkedIn'de paylaş (Yeni pencerede açılır) LinkedIn WhatsApp'ta paylaş (Yeni pencerede açılır) WhatsApp Pinterest'te paylaş (Yeni pencerede açılır) Pinterest Telegram'da paylaş (Yeni pencerede açılır) Telegram Reddit'te paylaş (Yeni pencerede açılır) Reddit Tumblr' da Paylaş (Yeni pencerede açılır) Tumblr Arkadaşınıza e-posta ile bağlantı gönderin (Yeni pencerede açılır) E-posta Daha fazla Yazdır (Yeni pencerede açılır) Yazdır Bunu beğen:Beğen Yükleniyor... İlgili Share on Facebook Share Share on TwitterTweet Share on Pinterest Share Share on LinkedIn Share Share on Digg Share Send email Mail