Crossrail Publishes ‘Realistic and Achievable’ Completion Plan Yurtdışı Haberleri by railsistem - Ekim 23, 20190 Crossrail Ltd has developed a new plan to complete the remaining works on the Elizabeth Line so that it can enter passenger service as soon as possible. Crossrail Ltd says this plan sets out a timeline that is both “realistic and achievable”. The plan has given rise to an in-depth delivery control schedule that will track 120 key milestones. Specifically, Crossrail says that final fit-out and testing and commissioning is scheduled to be completed by the end of the year at “many” stations. Crossrail also says it is on track to finish the fit-out and testing of the tunnels by January 2020. source= https://railway-news.com/crossrail-completion-plan/ Paylaşmak Güzeldir... Facebook üzerinde paylaş (Yeni pencerede açılır) Facebook X'te paylaş (Yeni pencerede açılır) X LinkedIn'de paylaş (Yeni pencerede açılır) LinkedIn WhatsApp'ta paylaş (Yeni pencerede açılır) WhatsApp Pinterest'te paylaş (Yeni pencerede açılır) Pinterest Telegram'da paylaş (Yeni pencerede açılır) Telegram Reddit'te paylaş (Yeni pencerede açılır) Reddit Tumblr' da Paylaş (Yeni pencerede açılır) Tumblr Arkadaşınıza e-posta ile bağlantı gönderin (Yeni pencerede açılır) E-posta Daha fazla Yazdır (Yeni pencerede açılır) Yazdır Bunu beğen:Beğen Yükleniyor... İlgili Share on Facebook Share Share on TwitterTweet Share on Pinterest Share Share on LinkedIn Share Share on Digg Share Send email Mail